PROJECT OVERVIEW

JackWolf Group won after competitively tendering through a grant funding decarbonisation scheme. We were employed by the school to carry out the design and installation of a fundamental energy efficient decarbonisation project.

CONTRACT VALUE: £391k

JACKWOLF'S SOLUTION

New technology often presents initial challenges, but through close collaboration with the manufacturers, these were effectively identified and resolved, ensuring the school received a fully operational and reliable system.

bg-brand-icon

PROJECT DELIVERY

The school has now decommissioned the gas meter supplying the plant room, eliminating gas costs and significantly reducing its carbon footprint.

We replaced their existing gas fired boilers with a renewable energy external air source heat pump (ASHP) and internal water to water heat pump (WWHP) to deliver 70°C heated water mitigating the need to increase existing heat emitters. 

We formed a new concrete base and acoustic enclosure to house the large,  external air source heat pump (ASHP). This heat pump delivered 45°C via a trench formed for the flow and return heating pipes going into the plant room located 20 metres away. The existing boilers were decommissioned and replaced with a single water to water heat pump (WWHP) which boosts the water from 45°C to 70°C. 

PROJECT OUTCOME

JACKWOLF Group implemented advanced ASHP/ WWHP technology, delivering a high temperature heating system which allowed the school to maintain its existing pipework and heat emitters without the need for costly upgrades.