PROJECT OVERVIEW

Jackwolf Group was awarded the MEP contract to replace boilers across 10Nr plant rooms around the Category B Prison.

Our remit was to replace the boilers while maintaining heating and hot water at all times within a live prison environment.  

CONTRACT VALUE: £500k

JACKWOLF'S SOLUTION

The project aimed to replace existing boilers that were end of life whilst maintaining services to the facility throughout the heating season. 

Jackwolf Group created and designed a bespoke pipework header system which allowed :

  • New boilers
  • New flues 
  • New pumps
  • New gas valves 
  • BMS modifications 

 

bg-brand-icon

PROJECT DELIVERY

Jackwolf Group were initially awarded 5Nr plant rooms and as a result of their successful performance, negotiated another 5Nr plant rooms split across 3 years. 

All works were handed back successfully in time for the facility to be handed back to HMPS from the PFI contract.  

PROJECT OUTCOME

Jackwolf Group were initially awarded 5Nr plant rooms and as a result of their successful performance, negotiated another 5Nr plant rooms split across 3 years. 

All works were handed back successfully in time for the facility to be handed back to HMPS from the PFI contract.  